Surface, colour, curing

    Powder coating & surface treatment

    Glintify calculates the total surface area directly from the part's geometry, including exposed and hidden surfaces. Weight is calculated for hanging on the conveyor. Masking areas can be defined per part or per part family. Colour change per batch is calculated with a setup cost for line stop and cleaning.

    // Detection

    What Glintify detects

    The system analyzes the part's geometry and extracts every manufacturing-relevant feature without manual input.

    Extracted data

    Total surface area, volume, weight, exposed surfaces, hidden surfaces

    // Automation

    What is calculated automatically

    All measurements are extracted directly from the geometry.

    Total surface area from STEP geometry
    Weight (for hanging on conveyor)
    Number of exposed sides
    Holes and cut-outs requiring masking
    // Quality

    Quality rules

    The system automatically checks whether the part fits within your capacity and flags designs that can cause production issues.

    Sharp edge < 0.5 mm → coverage issue
    Uncleaned surface → adhesion failure
    Blind hole with pocket → risk of powder buildup
    Colour shift between batches → documented
    // Setup

    Typical setup

    What a typical setup looks like for this operation.

    Hanging on conveyor per part
    Masking of threads, sealing surfaces, sliding tracks
    Colour choice per order/customer
    Quality test: adhesion, colour, layer thickness
    // Example

    Cost example

    Line-by-line breakdown of the part cost using your machine data and prices.

    Cost itemAmount
    Surface area 0.85 m²SEK 42.50
    Pretreatment (phosphating)SEK 8.50
    Masking 6 areasSEK 12.00
    CuringSEK 5.00
    Total coating costSEK 68.00
    // Costing in Monitor's format

    The same routing line as in Monitor

    On top of our time-based calculation, powder coating & surface treatment is also costed as a routing line ("beredningsrad") in Monitor's format: production group (work center), setup time, cycle time, allowance (F-time) and piece time, priced with the production group's cost factors. The line can be exported as an article with routing straight to your ERP system.

    Routing lineExplanation
    Production groupFetched from your ERP system or created from the machine park
    Setup timePer batch, not per piece — spread over the quantity
    Cycle timeThe technical time per piece, calculated from the geometry
    F-time %Allowance on top of the cycle time
    Piece timeCycle time × (1 + F-time %)
    Cost factorsMachine, wages + social charges and fixed manufacturing overhead in SEK/h, with a staffing factor
    Cost = setup time × rate + piece time × rate × quantity

    Markups for MO (material overhead), LO (subcontracting overhead), AFFO (general overhead) and profit are added at quote level — exactly as in Monitor's pre-calculation.

    Calculate your own part

    Upload a STEP file, we run the analysis and show exactly what the system detects for powder coating & surface treatment. No manuals, no calls.